You are the project manager on a defence project. The buyer wants to get an idea of how much he will pay for cost overruns. With the following variables, calculate the point of total assumption: Expected Cost=$150,000; Expected Profit=$37,500; Target Price=$187,500; Buyer/Share Ratio=60%/40%; Ceiling Price=$225,000; Maximum Overrun=150%.

(A)$201,875.00

(B)$223,125.00

(C)$212,500.00

(D)$191,250.00

--
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
---
You received this message because you are subscribed to the Google Groups "PMHUB - The largest PM group in Googlegroups!" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PMHUB+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

Post a Comment