A sponsor for a project in a manufacturing industry shares his experiences with a new project manager who has been appointed to manage new project. The sponsor clearly specifies that processes of the organization should be strictly followed so as to ensure the prevention of gold plating.
The project manager is in the process of documenting how the scope will be defined, validated and controlled. Which document is he preparing?
Options :
a, Quality assurance
b. Quality control
c. Scope management plan
d. Scope planning
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
---
You received this message because you are subscribed to the Google Groups "PMHUB - The largest PM group in Googlegroups!" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PMHUB+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment