You are conducting an electrical network and fixtures installation project. During project execution, your quality auditors highlighted some defects in the work performed. You analyze the situation and determine that these are genuine defects that need to be fixed. You submit a change request, which is approved and the team performs the necessary defect repairs. Which of the following is incorrect regarding this scenario?

A.) You have followed the change control system

B.) You have performed the Monitor and Control Project Work process

C.) You have performed the Integrated Change Control process

D.)You should document these defect repairs in the Project Management Plan


Sample questions (and also answers) here

http://www.pmhub.net/PMD/pm-prepcast-free-pmp-exam-questions-and-answers-pmbok-5/

--
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
---
You received this message because you are subscribed to the Google Groups "PMHUB - The largest PM group in Googlegroups!" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PMHUB+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

Post a Comment