PMHUB-G Crosswind PMP sample PMP Exam Problem

 Sign-off has just occurred on the project charter. There are items in the project charter that mandate a specific vendor and describe the maximum amount of physical and computer storage space available to the team. These are examples of what?

(A)Assumptions that impact the project

(B)Constraints that impact the project

(C)Risks of the project

(D)Activity resource requirements

--
--