A seller organization was executing work for a project under a contract. During the course of the project, a number of disputes arose over the scope and quality of work.
The project manager from buyer decided to verify compliance in the seller’s work processes and deliverables. Which of the following tools the project manager applied here?
Options :
- a. Inspections and Audits
- b. Alternative dispute resolution (ADR)
- c. Claims court
- d. Appeals court
answer is here:
http://www.pmhub.net/PMD/pmp-exam-questions-source-whizlabs-exam-simulator/
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
---
You received this message because you are subscribed to the Google Groups "PMHUB - The largest PM group in Googlegroups!" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PMHUB+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment