a) In some books(Rita Mulcay) the ES of
the first activity is taken as 0(zero) and early finish is
calculated as ES + duration = Early Finish
b) In some books(Head First) the ES of
the first activity is taken as 1(one) and the early finish
is calculated as ES + duration - 1 = Early Finish.
When the question is regarding "What is the ES of an
activity". Both the books give different answers.....