A project has the CPI of 0.73 and SPI of 1.1. Two programmers on your project team are in conflict over the best approach to take now. A junior programmer wants to re-use some of the software components your company developed from a similar software application in the past. She supports her idea by claiming that this approach would save at least 1,000 hours of team effort. The opposing senior programmer wants to follow the current development plan because the new proposed approach would require major design changes.


As the project manager, what is the best way for you to proceed?

 

A.) Tell both programmers to work out the problem between themselves

B.) Consult the project management plan for guidance

C.) Tell them to follow the original design

D.) Analyze the idea and issue a change request if appropriate


Answer here: http://www.pmhub.net/PMD/pm-prepcast-free-pmp-exam-questions-and-answers-pmbok-5/

--
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
---
You received this message because you are subscribed to the Google Groups "PMHUB - The largest PM group in Googlegroups!" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PMHUB+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

Post a Comment