The 91 housings are then being machined. After this process step 10 machined castings are found leaking. 3 of these items can also be saved using another sealing process for machined castings.
The remaining 84 housings are getting mounted to the power plant pipework. During a pressure test after this process step it is found that 12 valves are leaking. Out of these a number of 6 valves can be saved by replacing the sealing rings used.
Finally the project manager has 78 valves which he can use. What is true?
Options :
FTY = 0.91, RTY = 0.84
FTY = 0.65, RTY = 0.78
FTY = 0.84, RTY = 0.91
FTY = 0.78, RTY = 0.65
(source Lehman 75 problems)