-- You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished.
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A EAC = 550,000
B EAC = 525,000
C EAC = 500,000
D EAC = 425,000
You perform Earned Value Analysis and find the following results:
EV: 250,000; PV: 200,000; AC 275,000
BAC is 500,000.
What is right?
A EAC = 550,000
B EAC = 525,000
C EAC = 500,000
D EAC = 425,000