contractor with the following parameters:
Target cost: $1,000,000
Target contractor fee: $100,000
Cost benefit sharing ratio: 80%/20%
Price ceiling: $1,200,000
What is the Point of total assumption (PTA, Breakpoint) of the project?46
o $1,000,000
http://forums.pmhub.net/viewtopic.php?f=50&t=13730&p=33770&hilit=breakpoint
--