In a project, several risk response strategies are used to effectively
manage project risks. The strategy or mix of strategies should be used
when planning for risk responses. Which of the following statements
best describes an 'accept' strategy for negative risks or threats?
A.) Adopting less complex processes is an accept strategy.
B.) Use of insurance is part of an accept strategy.
C.) Using contingency reserve is part of accept strategy.
D.) Extending schedule is part of an accept strategy.
answer and explanation:
http://www.pmhub.net/forums/viewtopic.php?f=102&t=15791
--