PMHUB-G PMP Exam problem: Alternative schedules

The following PMP® exam sample question is taken from the Free PMP Exam Simulator at http://free.pm-exam-simulator.com - The answer is at the LINK


You developed alternative schedules based on best-case and worst-case scenarios on your project. You want to keep these alternative schedules stored in your project documents, in case of changes in project resources. Where would you store alternative schedules?

A.) Schedule Baseline

B.) Schedule Data

C.) Project documents

D.) Project scope statement

--