| You are running a public library construction project in which two key stakeholders are in continuous conflict with each other over location and design of the building. As a project manager, you have spent many hours resolving their conflicts, but it isn't getting any better. What should you do next? | Refer to the Project Charter for the escalation process | Refer to the Communications Plan for the escalation process | Involve the core project team | Involve the sponsor |
--