9. The retail ERP project is the largest the company has done in its history. There are a number of pieces of work the team has decompressed via a breakdown structure to better control the project. Of the following breakdown structures and descriptions, which is correct?
(A)Organizational breakdown structure, which graphically illustrates how project management is structured to accomplish project activities
(B)Risk breakdown structure, which lists risks grouped by probability of occurrence and listed by severity of impact
(C)Resource breakdown structure, which shows the type of resources used on the project
(D)Bill of Materials, which lists the cost of components, assemblies, and sub-assemblies used to build the product.
http://www.pmhub.net/PMD/crosswind-pmp-exam-success-series-exam-simulation-questions/
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
---
You received this message because you are subscribed to the Google Groups "PMHUB - The largest PM group in Googlegroups!" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PMHUB+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.
No comments:
Post a Comment