6. The project to create a new drill type for an oil exploration initiation has been in progress for twelve months. Of the following, what best describes when it closes?

(A)When the validate scope process is completed for the project

(B)When the project is canceled

(C)When the project funds are depleted

(D)All of the answers


answer:? 

http://www.pmhub.net/PMD/crosswind-pmp-exam-success-series-exam-simulation-questions/

--
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
---
You received this message because you are subscribed to the Google Groups "PMHUB - The largest PM group in Googlegroups!" group.
To unsubscribe from this group and stop receiving emails from it, send an email to PMHUB+unsubscribe@googlegroups.com.
For more options, visit https://groups.google.com/d/optout.

No comments:

Post a Comment