PMHUB-G Can you calculate SPI?

14. You are having a home theater room added to your house. The project should take 5 days and cost $1,500 per day to complete. After 3 days, the project is 30% complete and $5,000 has been spent. What is the SPI?

(A)0.45

(B)0.50

(C)0.40

(D)1.00


answer ?