Saturday, September 12, 2009

RES: PMHUB-G Pert Chart or Network diagram / Task or activities

Dr Chan
PERT is a mathematical method of estimation within 3 point estimation
(Optimistic+4xNormal+Pessimistic)/6 and that for not a diagram method. I
believe, the perversion of those terms is in part created by MS, when they
used in early versions of MS-Project the term PERT/CPM Network, changed to
Network diagram in version 2000. But you can find the term even in early
books from Max Wiedeman and others.

Activity vs. Task: This isn't a PMISM, but a language definition:
Activities have Tasks. Expl.: Your activity is to clean up the room. One of
the tasks should be to clean the table.

Hope having been able to help

Rgds
Gerhard Tekes, PMP, OPM3-CC
3pta@3pta.com.br
+55-71-3012.6611

-----Mensagem original-----
De: PMHUB@googlegroups.com [mailto:PMHUB@googlegroups.com] Em nome de dr
chan
Enviada em: sábado, 12 de setembro de 2009 01:05
Para: PMHUB - The largest PM group in Googlegroups!
Assunto: PMHUB-G Pert Chart or Network diagram / Task or activities


Can you please elaborate why we call Network diagram a pert chart most
of time i know its wrong but why??
Second i have read somewhere we have to say activities instead of task
is that PMISM or what ??

Please elaborate
Thanks in advanced

Dr Chan


--~--~---------~--~----~------------~-------~--~----~
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
-~----------~----~----~----~------~----~------~--~---

No comments:

Post a Comment