You found the following Earned Value Analysis information for a recently closed out project:
SPI = 0.7, CPI = 1.0
A: The project has been cancelled while it was executed. At that time the project was behind schedule and on budget.
B: The project's deliverables have all been finished. The project came in behind schedule but on budget.
C: The project's deliverables have all been finished. The project came in ahead of schedule but on budget.
D: The project's deliverables have all been finished. The project came in on schedule but over budget