C is the correct answer.  Why would anyone put in a change order with no knowledge of the subject?  Even without knowing Project Mangement, common sense would dictate that the experts need to speak and a decision made from that point.

That group leaving the responses does not sound like they know what they are doing.  The ones who said D is the correct answer have no common sense whatsoever.
 

--- On Fri, 4/1/11, PMHUB <pmhub@pmhub.net> wrote:

From: PMHUB <pmhub@pmhub.net>
Subject: PMHUB-G What is the right answer to this PMP Exam question?
To: "PMHUB" <PMHUB@googlegroups.com>, pmhub@yahoogroups.com
Date: Friday, April 1, 2011, 8:51 PM

8. You are managing a project and the customer's engineer visits your facility on an inspection and general getting acquainted tour. During the tour they make the comment that the parts that are being designed should be in stainless steel instead of plain steel with enamel. What should you do?

a. Authorize the change in design to your engineers
b. Continue with the present design
c. Speak to the visiting engineers and discuss having an informal meeting between
your engineers and the visiting engineers
d. Ask the visiting engineers to submit a change proposal to the change system

Experts, what is the correct answer here?
Discussions on what is the right answer here:

http://www.pmhub.net/forums/viewtopic.php?f=50&t=15322
--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en

--
To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en

No comments:

Post a Comment