remains even after you implement all of your response strategies. What kind of risk is this and what should you
do about it?
It's a secondary risk. You don't need to worry about it.
It's a residual risk. You need to plan a response strategy for it.
It's a residual risk. You don't need to plan a response strategy for it because you've already implemented all of
the risk responses you can plan for.
It's a contingency reserve. You should only use it if the first risk occurs.
check here:
-- To post to this group, send email to PMHUB@googlegroups.com
To unsubscribe from this group, send email to PMHUB-unsubscribel@googlegroups.com
For more options, visit this group at http://groups.google.com/group/PMHUB?hl=en
No comments:
Post a Comment