You are conducting a status meeting and monitoring your risk register when you discover a risk that
remains even after you implement all of your response strategies. What kind of risk is this and what should you
do about it?
It's a secondary risk. You don't need to worry about it.
It's a residual risk. You need to plan a response strategy for it.
It's a residual risk. You don't need to plan a response strategy for it because you've already implemented all of
the risk responses you can plan for.
It's a contingency reserve. You should only use it if the first risk occurs.